SayPro Manage project baselines through integrated change control.

Perform Integrated Change ControlProject almost never run exactly according to the plan and changes, accordingly, changes are a normal part of project management. Integrated change control is performed constantly throughout the entire project life cycle to effectively manage the change process. The integrated change control process includes reviewing all change requests as well as approving and managing changes to any of the following: deliverables, organizational processes, project documents and the project management plan. The following activities are part of integrated change control:• Identifying that• A change is needed or• A change has occurred• “Influencing factor” that lead to informal, uncoordinated changes (i.e. preventing people from circumventing the required process). Informal changes often lead to a phenomenon known as “scope creep”• Reviewing, analyzing and approving requested changes promptly (usually done by a CCB, i.e., change control board .However, small changes may be designated to another party so that the CCB can pay proper attention to larger, more significant changes).• Managing approved changes• Maintaining the integrity of established baselines (i.e. You must adjust current baseline to reflect approved changes)• Reviewing and either approving or denying all recommended preventive and corrective actions.• Coordinating the effect of changes across the entire project (e.g., A change in the schedule may affect cost, quality, risk and staffing requirements).• Documenting the likely impact of requested changes (CCB).Configuration management and change control work together to accomplish three primary objectives:• Establish a consistent method for requesting changes to established baselines. The system must assess the potential value of all requested changes.• Improve the project by evaluating the likely impact of all requested changes (i.e., approve good changes and reject bad ones).• Provide effective communication mechanisms so that stakeholders are aware of all changes.Other key information about changes control:• Change control operates within the configuration management system. A major goal of change control is to control emerging scope against the baseline.• Changes may be requested at any time by any stakeholder.• Verbal change requested should always be recorded in written form.• Many changes systems use a CCB (change control board) for approving or disapproving change requests.• However, project managers may be authorized to approve certain change requests (e.g., if the likely impact is below established cost or schedule thresholds).• In some cases, changes may be approved by the customer (as per contractual provisions)• On large projects, multi-tiered CCBs, with different responsibilities, may exist (e.g., technical review versus cost or different CCBs for each project within a program)• Change systems often include provisions to handle emergency changes without prior reviews. In such cases, the change is usually documentary as soon as practical.• Every change request must be either accepted or rejected with documentary to support the decision.

Perform Integrated Change Control
Inputs Tools Outputs
1. Project management plan2. Work performance information3. Change requests4. Enterprise environment5. Organizational process assets 1. Expert judgment2. Change control meeting 1. Change request status updates2. Project management plan updates3. Project document updates

Five Key Inputs for Perform Change Control:

  1. Project Management Plan: Provides the current, approved plan that may be affected by any approved changes.

  2. Work Performance Information: Provides the actual status of project activities and as such, may indicate where problems exist that requires changes.

  3. Change Request: This is the only instance in the site in which change request are an input. In the rest of this site, change requests are outputs to 2 of 20 planning processes, 5 of 8 executing processes and all 10 monitoring and control processes.

  4. Enterprise Environment Factors: Specific environmental factors that may influence integrated change control include: Project management information systems (scheduling tools, configuration management system and information collection and distribution systems

  5. Organization Process Assets: The specific organizational process assets that may affect nitrated change include:

• Change control procedures• Procedures for approving and issuing change authorizations• Process measurement database (collect data on status of processes and products)• Project files (scope, schedule, cost, calendars, network diagrams, risk registers, risk response plans)• Control management knowledge baseTwo Key Tools Perform Integrated Change Control:

  1. Expert Judgment: In this case, it is important to get right subject matter experts on the CCB.
  2. Change Control Meeting: Meeting by the CCB to review change requests and either approve or reject each request.

Three Key Outputs for Perform Integrated Change Control

  1. Change Request Status updates:

• Approved change requests are implemented though Direct and Manage Execution and updates are made to project documents• Disapproved change requests are documented as such in the change request log.

  1. Project Management Plan Updates: Subsidiary management plans and baselines are updated, as needed.
  2. Project Document Updates: The change request log and any documents that are subject to the formal change control process are updated, as needed.

Other Information about Integrated Change Control: Change control operates as a subset of the configuration management system. Configuration management provides the following functions:

  1. The first major step (performed early in the project life cycle) identifies the functional and physical characteristics of the product. This step result in the establishment of three key baselines ( scope, time and cost)
  2. The next major step controls changes to those baselines and keeps careful records of the status of each change.
  3. The final step audits the final results to verify conformance to requirements (including any approved changes)

Communications and stakeholder engagement strategiesA key element of sustaining and embedding any innovation project is to communicate with stakeholders effectively and to engage them as early on as possible with the project. It is worth spending time on developing a communications and stakeholder engagement strategy and plan to enable the project team to:Better understand the needs and concerns of different stakeholders.Different stakeholders will have different needs and concerns – for instance, practitioners are more likely to want to know why they should adopt and prioritise your project (as opposed to other innovations), if there is good evidence to support its pedagogical value, how it will benefit them/their students and the degree of support that they can expect, whilst heads of faculties/schools/departments maybe more likely to be concerned with resourcing, budgets and how to integrate innovations into their policies/plans.Develop a shared understanding of what they want to achieve by communicating and engaging with each stakeholder group.Too often, projects are concerned with purely producing the project outputs that they specified in the project plan. However, these outputs will be meaningless unless they are adopted by stakeholders – in the short, medium and long term. It is therefore worthwhile identifying what they want to achieve for each stakeholder group and ensuring these outputs are usable. For example, defining how many academics/teaching staff will make an informed choice as to whether they wish to adopt the innovation or establishing whether or not the innovation has been integrated into institutional or faculty/school/departmental strategies, processes, services and systems. It must, however, be recognised that projects may have to carefully balance the articulated needs from different stakeholder groups.Collaboratively develop a common set of key messages to communicate to different stakeholders as well as a plan to use both traditional and new media communications techniques.It is not uncommon to find different project team members giving out totally different key messages about the project. A collaborative exercise to develop key common messages about the innovations project will help to provide a more coherent approach to engaging with different stakeholders. Having stated that the development of “shared messages” is important, the emphasis on communications must be on interaction, dialogue and engagement – bearing in mind that the word “dissemination” has a rather one-way feeling about it!The diagram below illustrates a suggested approach to developing a communications and stakeholder strategy and plan.An example of a completed communications and engagement strategy can be seen for the University of Oxford CASCADE project within the JISC Transforming Curriculum Delivery programme.Communications plans should aim to convey simple messages based on the WHY – WHAT – WHEN – WHO – HOW principles e.g.• WHY: Why should academic/teaching staff change their teaching and learning practices?• WHAT: What should academic/teaching staff change in their teaching and learning practices?• WHEN: When best to make changes e.g. at curriculum review time?• WHO: Who needs to be involved in the change?• HOW: How to make the changes e.g. is it a DIY approach and what support is available?An excellent example that demonstrates effective communications is how the TESEP project based at Edinburgh Napier University helped to transform teaching and learning by providing simple messages e.g. based on:• Why do we need to change learning and teaching practice?• Planning to transform.• Rethinking your practices.• Transformation stories.1

2 Rebecca Maapola | SayPro Administration ManagerSayProWebsite: www.saypro.onlineCell: 27 (0) 71 240 2557Email: rebeccaStudy and Qualifications www.saypro.online Our Company www.saypro.online

SayPro is a group of brands leading in Africa’s development, building innovative online solutions and a strategic institution on child growth, youth empowerment and adult support programmes, applications in Africa.SayPro Core Skills and Expertise:

  • SayPro Artificial Intelligence, Graphics, Online Design and Web Development
  • SayPro Higher Education, Certification, ELearning Development, Qualification Design and Online Training.
  • SayPro Community Development in Youth Unemployment, HIV/AIDS, Human Rights and Gender-Based Violence
  • SayPro Company Registrations, Tax, VAT and Website Designs.
  • SayPro Research, Opportunity Sharing in Tenders, Funding and Contact Directories.
  • SayPro Monitoring, Evaluation, Knowledge Management, Learning and Sharing.

SayPro is providing international and global opportunities for African youth. Partner with SayPro now by sending an email to info or give us a call at + 27 11 071 1903Please visit our website at www.saypro.online Email: info@saypro.online Email: info@saypro.online Call: + 27 11 071 1903 WhatsApp: + 27 84 313 7407. Comment below for any questions and feedback. For SayPro Courses, SayPro Jobs, SayPro Community Development, SayPro Products, SayPro Services, SayPro Consulting, and SayPro Advisory visit our website to www.saypro.onlinePlease visit our website at www.saypro.online Email: info@saypro.online Email: info@saypro.online Call: + 27 11 071 1903 WhatsApp: + 27 84 313 7407. Comment below for any questions and feedback. For SayPro Courses, SayPro Jobs, SayPro Community Development, SayPro Products, SayPro Services, SayPro Consulting, and SayPro Advisory visit our website to www.saypro.online